Project information
Located in a prime central area of Thao Dien, District 2, Masteri Thao Dien is a symbol of luxury development, offering residents a premium living experience with panoramic city views. The project also prioritizes the construction of a smart parking system Thao Dien Mall to meet residents’ growing parking needs and ensure convenient mobility. Together, these features create an ideal living environment for those seeking comfort and modernity.

Masteri Thao Dien is a premium mixed-use development featuring a shopping mall, office buildings, luxury apartments, and green parks. Its direct connection to An Phu Station on Metro Line 1 provides convenient access to District 1 and neighboring districts in just seven minutes. Located only 200 meters from the Saigon River, the development offers residents an airy living environment with abundant natural light and fresh breezes.
The project comprises four residential towers ranging from 41 to 45 floors, with more than 3,000 apartments measuring 46–160 m², as well as a tower incorporating offices, a hotel, a school, and commercial facilities.
Challenges of the smart parking system Thao Dien Mall
- Installation address: Thao Dien Shopping Center, District 2, Ho Chi Minh City
- Facility type: Residential development combined with commercial services
- Scope of work: Design, supply, and installation of an automated parking system, car lifts, and vehicle access control system
- Implementation year: 2016
Viet Chao’s solution as the contractor
- Brand: XIZI iParking
- Model: PSH-2 puzzle parking system
- Site area: 8 hectares
- Designed parking capacity: 232 spaces
- Actual implementation year: 2016
Challenges of smart parking system construction in District 2
Site conditions
Challenges
Based on the site inspection results, the clearance height of one car lot at parking position No. 07 in Building CT4 did not meet the requirements for system operation due to interference from a basement support column.
Solution
Viet Chao proposed the most practical solution to the client: suspend the operation of the affected car lot and proceed with a settlement to deduct the installation cost for parking position No. 07 in Building CT4. The deduction amounted to nearly USD 2,000 for the affected parking space.
Lessons learned
First, site surveys and clearance measurements must be conducted thoroughly at the early stages of a project. Identifying dimensional issues in advance helps prevent significant losses and modifications during construction. Close coordination among all parties is also essential to verify actual site measurements against the design drawings.
Second, when technical issues cannot be resolved, proposing a reasonable and transparent alternative is crucial. Viet Chao handled the situation professionally by recommending that the affected parking space be taken out of operation and proposing an appropriate cost deduction. This demonstrated the contractor’s sense of responsibility and flexibility in problem-solving.
Finally, effective risk management and contingency planning are essential for every project. Although removing one parking space may result in a financial loss, accepting this reduction to ensure the safety and reliable operation of the entire system was the right decision, reflecting the contractor’s professionalism and credibility.
Project maintenance and operation in Thao Dien
![]() |
![]() |
![]() |
![]() |
With over 20 years of industry experience, Viet Chao has continuously developed and refined smart parking solutions across a wide range of projects. The smart parking system Thao Dien Mall, along with our other smart parking projects, has presented unique challenges and difficulties. These experiences have helped us gain valuable insights and continuously improve our technical capabilities and service quality. Customer satisfaction is our measure of success.