Project information
As urbanization continues to accelerate, the demand for parking facilities has become increasingly urgent, particularly in dynamic areas such as District 4. Expected to become one of the country’s major economic and financial hubs, the project aims not only to provide a modern living environment but also to attract a well-organized residential community. Therefore, smart parking system construction in District 4 for the DeLaSol project represents not only a technical challenge but also an opportunity to enhance the quality of life for local residents.

The DeLaSol project, also known as Summer, was developed by CapitaLand and is located directly on Ton That Thuyet Street. In addition to its convenient transportation access, the project benefits from a wide range of nearby amenities.
Challenges faced by the developer
- Construction address: Ton That Thuyet Street, District 4, Ho Chi Minh City
- Facility: Residential development combined with commercial services
- Scope of work: Design, supply, and installation of the automated parking system
- Implementation year: 2018
- Developer’s requirements:
CapitaLand is one of Asia’s largest real estate groups. Headquartered in Singapore, this multinational company operates primarily in real estate, serviced residences, and real estate financial services, focusing on developments in major cities across the Asia-Pacific region and Europe.
Total number of premium apartments: 870 units. Therefore, the developer required a large parking capacity that could meet the following requirements:
| Space optimization | – Reduce space requirements by 60–70% compared with traditional parking facilities. – Make efficient use of underground space. – Free up more space for other project amenities. |
| Safety and security | DeLaSol is designed exclusively for residential apartments, with no officetel units, helping ensure residents’ security and privacy. Therefore, the smart parking system must also meet the following requirements: – Install a surveillance camera system. – Protect vehicles from collisions and avoidable accidents. – Ensure user safety. |
| Environmental friendliness | – Reduce vehicle emissions inside the basement. – Save energy used for lighting and ventilation. – Contribute to the development of a green building. |
| Alignment with modern trends | – Meet the expectations of residents in luxury residential buildings. – Enhance the value and prestige of the premium development. – Attract and retain customers through modern technology and equipment. |
Viet Chao’s smart parking system solution in District 4
-
Brand: XIZI iParking

- Model: PSH-2 puzzle parking system
- Land area: 1.45 hectares
- Designed facility: Three basement levels with over 300 parking spaces
- Actual implementation period: 2019
Smart parking system construction process in District 4
Site handover challenges during construction
Challenges
On February 13, 2023, we completed the mechanical installation for 199 parking spaces where the site had been handed over. However, the remaining 82 spaces had not yet been handed over to us.
The same challenge persisted on May 13, 2023. By that date, Viet Chao had completed the mechanical installation for 272 parking spaces and the electrical installation and commissioning work for 203 spaces. However, construction could not begin at 9 of the 281 parking spaces because the site had not yet been handed over to our contractor.
Solutions
We formally notified the developer that the delayed handover of the remaining nine spaces would prevent us from guaranteeing 100% completion of the contractor’s scope of work, as well as the inspection and acceptance of the completed installation.
Nevertheless, Viet Chao remained committed to completing the installation of the aforementioned 272 out of 281 parking spaces according to the original schedule, before May 31, 2023.
We also informed the developer that any schedule delays or additional costs arising from the late handover of the site, contrary to the agreed schedule, would not be our responsibility.
Lessons learned
First, site handover planning and schedule management must be prioritized from the beginning of the project. This allows both parties to clearly define the timing, conditions, and procedures for each stage of the handover, preventing delays that could affect the overall project schedule.
Second, timely communication and reporting of difficulties and obstacles are essential. We ensured that the developer was clearly informed of the delayed site handover and its potential impact on the project.
Third, contingency planning and flexibility in implementation are necessary. Despite the challenges posed by the nine spaces that had not yet been handed over, the contractor remained committed to completing the work that could proceed—272 out of 281 parking spaces—on schedule. This demonstrated our sense of responsibility and ability to adapt effectively to changing circumstances.
Construction schedule
Challenges
Under the original plan and contract, Viet Chao was scheduled to complete construction for the 272 parking spaces handed over by May 31, 2023. However, at the developer’s request, the completion deadline for these 272 spaces was brought forward to May 15, 2023.
Solutions
We respectfully requested that the developer confirm its support for the additional costs incurred to meet the accelerated completion schedule.
Lessons learned
An important lesson is the need for clear agreements and formal written documentation for all changes to the project schedule. When the developer requested an earlier completion date than originally planned—bringing the deadline forward from May 31 to May 15—the contractor responded professionally by proposing a solution to address the additional costs. This approach not only protected the contractor’s interests but also demonstrated a cooperative attitude and willingness to meet the developer’s requirements under reasonable conditions.
Advantages of smart parking system construction in District 4
Equipment delivered on schedule
In accordance with the contract, we arranged the order and delivery schedules with the manufacturer. The project’s equipment was divided into two shipments: Lot 1 consisted of nine 40-foot containers, while Lot 2 consisted of three 40-foot containers.
Although the expected delivery schedule depended on various factors, including customs clearance procedures and the preparation of on-site storage space, our close monitoring and proactive coordination ensured that the equipment arrived at the project site according to the schedule specified in the contract signed by both parties.
Project photos after completion


Warranty and maintenance photos at the project
![]() |
![]() |
With over 20 years of industry experience, Viet Chao has continuously developed and refined smart parking solutions across a wide range of projects. Each project presents unique challenges, helping us gain valuable experience and continuously improve our technical capabilities and service quality. Customer satisfaction is our measure of success.