Project information for smart parking in Nam Tu Liem
Masteri West Heights occupies a prime location in the heart of Smart City, one of Hanoi’s most desirable urban developments. The project overlooks a 4.8-hectare central lake and offers open views of three interconnected parks. With its high-quality standards, this luxury residential development has attracted significant attention in the real estate market. However, one key question remains: Which contractor will undertake the smart parking in Nam Tu Liem District?

Designed by world-renowned partners, the luxury Masteri West Heights residential development sets an international standard of living with a unique, multi-level amenity system, featuring 22 exclusive amenities and 29 facilities within its internal parks.
Challenges raised by the developer
- Installation address: Tay Mo, Nam Tu Liem District, Hanoi
- Project: Mixed-use residential, business, and commercial development
- Scope of work: Design, supply, and installation of an automated parking system, car lifts, and vehicle access control system
- Completion year: 2023
- Developer’s requirements: In addition to durability, stable operation, and resident safety, the developer sought to incorporate the latest technologies into the project, such as one-touch software for checking available parking spaces and real-time notification systems.
Viet Chao’s proposed solutions
- Brand: XIZI iParking
- Model: PSH-2 puzzle parking system
- Parking capacity: 80+ vehicles
- Installation location: Basement levels
- Actual implementation period: 2023
Smart parking system in Nam Tu Liem | Process?
Work schedule coordination between both parties
Challenges
The contract required the parking system to be commissioned before June 2023. However, by the end of March, Viet Chao had still not signed the contract, received the advance payment, obtained approval for the shop drawings, or secured approval for the material list.
The main reason was that Viet Chao was a subcontractor to the general contractor and therefore lacked a formal legal basis (a signed contract) for the general contractor to approve its submissions.
These delays affected the procurement of imported equipment, making it difficult to meet the required project schedule.
Solutions
-
Viet Chao proactively proposed changing the contract arrangement from signing through the general contractor to signing directly with the developer.
- Streamline and optimize the submission approval, contract advance payment, and payment processes to help ensure the project schedule.
-
We were prepared to withdraw from the project because we could not guarantee compliance with the required contract schedule.
Lessons learned
-
Legal and contractual matters: We must ensure that all necessary legal documentation is in place before starting a project. Contract terms should also be clarified to prevent delays during implementation.
- Work processes: Both parties should simplify and streamline their procedures to avoid unnecessary delays.
-
Professionalism: Being prepared to withdraw from a project when the agreed schedule cannot be guaranteed is a professional decision. Reputation and execution capability are more important than accepting projects at any cost.
Coordination with other contractors
Challenges
Each contractor on a project has strengths in different areas of expertise. Misunderstandings during project implementation are therefore sometimes unavoidable.
Issues and questions raised by the parties involved included power supply, design drawings, site conditions, and other related matters.
Solutions
Viet Chao promptly addressed all questions and concerns raised by the developer and other contractors as follows:
1.How many power supply connection points are there with the general contractor for this parking system?
=> The matter has been discussed and agreed upon by all parties, and there are three power supply connection points.
2. Is the parking space availability indicator system installed on Basement Level B2?
=> Basement Level B2 is equipped with the system.
3. How are the cable conduits and wiring connections arranged in the layout?
=> This question can be understood in two ways: the power cables running from the supply points to the system, or the power cables routed within the parking system.
4. Please provide additional details on the types of electrical cabinets and control panels, installation schematic diagrams, and electrical and control system connections for the parking facility.
=> We cannot provide additional details because the equipment is 100% imported as a complete, integrated package. The operating instructions and technical documents have been provided from the beginning.
5. How are the barriers installed? Are automatic barriers provided at the parking spaces?
=> The system is equipped with automatic barriers. We will install them after completing all the mechanical and electrical work on the system.
Lessons learned
- Respond promptly to questions and concerns raised by the developer and other contractors.
-
Streamline and optimize workflows among all parties to ensure smooth coordination between contractors during project implementation.
Site conditions
Challenges
During the finalization of the material list to be attached to the contract for the “Design and Construction of the Automated Parking System” package, discrepancies were identified in several material items and suppliers compared with the tender documents we had previously submitted.
Solutions
- Proactively submit an official letter to the developer to notify them of the changes.
- Commit that the materials and suppliers in the revised submission are of equivalent or higher quality than those previously specified in the tender documents.
Lessons learned
- Transparency: Always proactively and honestly notify the developer of any changes to materials or supplies.
- Quality commitment: Ensure that all changes maintain or improve the quality of the original proposal. We will also provide sufficient supporting evidence to demonstrate that any replacement materials are equivalent to or superior to those originally proposed.
-
Professionalism: Take the initiative to address issues promptly and always prioritize the developer’s interests and benefits.
See more : Smart Parking in Bac Giang – Solutions by Viet Chao
Some maintenance photos of the Masteri West Heights parking system