As urbanization continues to accelerate, providing efficient and intelligent parking facilities has become an increasingly urgent need. The construction of a smart parking in Da Nang not only optimizes space utilization but also enhances the experience of residents and visitors. Da Nang Times Square stands out as a remarkable landmark, rising proudly along My Khe Beach, renowned as one of Vietnam’s most attractive beaches. With its exceptional location and impressive architecture, this premium complex, developed by Kim Long Nam Group, also sets a new standard for urban living through its integrated smart amenities.
Project information for Da Nang Times Square
Boasting four valuable frontages along two major thoroughfares, Vo Nguyen Giap and Pham Van Dong, Da Nang Times Square offers excellent connectivity to the city center and international airport. With the coastal city’s strong tourism and economic potential, this mixed-use complex features a bustling shopping center, luxury hotels, and premium apartments, promising to attract a large number of residents, tourists, and vehicles. The challenge for the developer is not only to create an upscale living environment but also to ensure a modern, convenient automated parking system that meets growing demand.
Challenges faced by the developer
- Project address: Pham Van Dong Street & Vo Nguyen Giap Street, Son Tra District, Da Nang City
- Project type: Residential complex combined with commercial services
- Scope of work: Design, supply, and installation of an automated parking system and vehicle access control system
- Implementation period: Late 2024–2025

Viet Chao’s smart parking solution in Da Nang
- Brand: XIZI iParking
- Model: PSH-2 puzzle parking system
- Project area: Total site area of 2.1 hectares, with a building density of 42%, of which the building footprint covers 1.58 hectares
- Total investment: VND 5.036 trillion
- Actual implementation timeline: Kick-off date: September 26
Challenges during smart parking system construction in Da Nang
Site conditions
During project implementation, Viet Chao also faced several challenges, particularly regarding the delivery of equipment to the site.
Challenges:
- Sea transportation made it difficult to determine the exact daily delivery schedule, especially when weather conditions were unfavorable.
- Most of the equipment and materials were imported as complete sets, making it impractical to deliver small quantities to the construction site separately.
Solutions proposed by Viet Chao to minimize the impact of these challenges:
- Upon receiving official notification of the equipment arrival date, Viet Chao will conduct a detailed site survey to prepare for installation.
- A detailed inspection and acceptance plan will be submitted to the developer before installation begins, ensuring transparency and close coordination.
- Despite external factors that may affect the detailed schedule, Viet Chao remains committed to meeting the overall project timeline.
Advantages during smart parking system construction in Da Nang
Effective coordination between both parties
The developer created favorable conditions for contractors, particularly Viet Chao, throughout project implementation:
- The developer proactively provided updates and closely coordinated with the contractor at every stage of the project.
- Basement floor and slab waterproofing had been completed, ensuring the technical conditions required for the automated parking system to operate.
- The three-phase power supply, in accordance with the approved design, had been provided, facilitating system connection.
- The vehicle control platform on basement level B1 had been constructed and was ready for the installation of the vehicle access control and monitoring system.
Viet Chao’s solution as the contractor
Viet Chao’s outstanding capabilities
From the early stages of the project, Viet Chao demonstrated a proactive approach and effective project management, working seamlessly with all stakeholders. With a team of experienced engineers and specialists in smart parking systems, we implemented each stage systematically, from detailed design and equipment selection to scientific construction planning. As a result, the smart parking system at Da Nang Times Square was completed ahead of the contractual schedule.
During project implementation, a technical issue arose regarding the required bolt material and coating. The supervision consultant requested that the connecting bolts be hot-dip galvanized. However, drawing on our technical expertise and hands-on experience from more than 50 projects, Viet Chao proactively conducted a detailed technical analysis of the advantages of each option under the conditions of this coastal project:
- Electro-galvanizing produces a thinner, brighter, smoother, and more aesthetically pleasing coating. As the project is located near My Khe Beach, where salt concentrations are high, electro-galvanizing was considered a suitable option because it provides effective protection for small components and helps prevent localized corrosion.
- XIZI products are manufactured under strict quality control procedures. Electro-galvanized bolts still meet all requirements for load-bearing capacity, corrosion resistance, and mechanical durability within the system.
- Hot-dip galvanizing involves high temperatures that may increase the risk of hydrogen embrittlement in certain types of high-strength steel. Electro-galvanizing is performed at lower temperatures, reducing this risk and helping maintain product safety and service life.
Through continuous efforts and proven professionalism, Viet Chao has established its position as a leading provider in Vietnam’s smart parking industry. We not only deliver advanced smart parking solutions but also provide developers with greater peace of mind and added value through effective project management, flexible problem-solving, and a strong commitment to quality, please contact us via hotline: Sales – 089 8552 888 / Technical support – 0906 00 77 00 for detailed consultation.