Project information
Located directly on Tran Hung Dao Street, MB Sunny Tower is close to major shopping centers and just a 3-minute drive from Ben Thanh Market. The area has a high concentration of foreign residents and visitors, as well as numerous hotels, restaurants, cafes, and office buildings. The tower also offers convenient access to Districts 3, 4, 5, 6, 7, 8, and 10, making the installation of a smart parking system in District 1 a practical necessity.
This major two-way road connects District 5 to District 1. The automated parking system is designed to provide convenient parking, control vehicle entry and exit, and ensure maximum security within the parking facility. These features help improve residents’ quality of life and enhance convenience for everyone using the building.
Challenges raised by the developer
- Installation address: 259 Tran Hung Dao Street, District 1, Ho Chi Minh City
- Project: Mixed-use building for residential, business, and commercial services
- Scope of work: Design, supply, and installation of an automated parking system
- Implementation year: 2015
- Developer’s requirements:
Viet Chao’s proposed solutions
- Brand: XIZI iParking
- Models: PSH-2 puzzle parking system and PJS2 vertical lifting parking system
- Parking capacity: 51 vehicles for the XIZI system (49 vehicles with PSH-2 and 2 vehicles with one MINI 31A unit), plus the PJS system
- Site area:
- Project design:
- Actual implementation year: 2015
Smart parking system installation process in District 1
Challenges
Site conditions
Challenges
A fire occurred in the generator room’s heat exhaust area on Basement Level B3 on January 19, affecting the construction work and project schedule.
Solutions
Upon receiving the notification, our team immediately arrived on-site to assess the actual conditions following the incident.
- All equipment remained unaffected by the fire thanks to the partition wall.
- The water level on the basement floor was 3 cm on the evening of January 19, causing no damage to the installed equipment.

- Other equipment was also unaffected thanks to protective covers and proper storage.

Lessons learned
- Improve construction safety awareness among all contractors and workers involved in the project.
- The developer should assign personnel to conduct inspections after each work shift to ensure the highest possible level of construction safety.
Construction schedule for the smart parking system in District 1
Challenges
Due to adverse weather conditions and storms in the East Sea, the shipment was delayed during transportation, resulting in the equipment arriving at the project site later than expected.
The equipment arrived at Ho Chi Minh City Port on December 15, 2014. Viet Chao Joint Stock Company is expediting customs clearance procedures to transport the equipment to the project site.
Solutions
As the building was already operational, additional time was required for site access and construction procedures. Some forklifts also had to operate at night, further extending the construction timeline. The contractor therefore proposed the following completion schedule and commitments:
- Equipment delivery to the project site: Before December 24, 2014.
- Installation completion: Before January 30, 2015.
Lessons learned
The delay beyond our committed schedule affected the project’s operation. We sincerely apologize to the developer, project management team, and supervision consultant, and respectfully ask for their understanding and consideration. We will make every effort to accelerate the installation process and make up for the delay.
Information submission
Challenges
Due to several errors in the information submitted by Viet Chao, we promptly issued an official letter explaining the technical specifications and proposing inspection, acceptance, and handover procedures as soon as the errors were identified.
Solutions
We would like to clarify the following technical features: vehicle height sensors and load weighing.
-
Vehicle dimension sensors: Sensors detect a vehicle’s length and height as it reverses into a parking space. An audible alarm is triggered if the vehicle exceeds the permitted length or height. The alarm remains active and prevents the system from operating until qualified technical personnel or a manager inspects the issue and resets the system. The system can resume operation only after the reset is completed.
-
Overload warning function: According to the tender documents, this was a translation error on our part. We mistakenly translated “overtime” (exceeding the waiting time) as “overload.” Furthermore, under the contract and its appendices, each parking unit is equipped with warning signs specifying the permitted vehicle dimensions and weight limits.
Lessons learned
-
Carefully verify all technical information before submission to prevent errors or confusion that could lead to misunderstandings.
- When an error is identified, promptly provide a clear, transparent, and detailed explanation to avoid unnecessary misunderstandings among the parties involved.
-
Improve the contractor’s information review and verification procedures before publication or submission, while strengthening the accountability of all relevant parties.
Maintenance of the smart parking system at MB Sunny Tower

![]() |
![]() |
![]() |
![]() |